After multiple delays and much anticipation, Bengaluru’s Namma Metro Yellow Line, connecting RV Road to Bommasandra via the bustling Electronic City corridor, is finally nearing completion. As the city battles traffic congestion and mounting urban pressure, the 18.8 km elevated stretch is expected to significantly ease commute times for lakhs of residents in the southern tech belt.
Civil works completed, final testing underway
The Bangalore Metro Rail Corporation Limited (BMRCL) has confirmed that civil works, including all 16 elevated stations across the Yellow Line, have been completed. Interior station finishing, platform installations, passenger amenities, and Communication-Based Train Control (CBTC) signaling systems are now fully in place.
The Yellow Line will offer much-needed connectivity to key zones like Electronic City, Bommanahalli, HSR Layout, and Silk Board, linking them with the Green Line at RV Road interchange and eventually the upcoming Blue and Pink Lines.
Safety inspections to begin mid-July
The final safety green signal is awaited from the Commissioner of Metro Rail Safety (CMRS). The Independent Safety Assessment (ISA), a crucial prerequisite, is set to begin post-July 15. Officials believe the inspections and approvals should be completed swiftly, barring any technical red flags.
Expected launch timeline: Late July to early August
With most infrastructure in place and test runs underway, BMRCL officials are targeting a phased launch between late July and early August 2025. If safety inspections proceed smoothly, the line may open initially with partial services, followed by full operations as more trainsets are inducted.
This timeline marks a significant step forward for Bengaluru’s metro network, which has faced repeated delays due to procurement issues, COVID-19 disruptions, and regulatory hurdles.
What the Yellow Line means for commuters
Civil works completed, final testing underway
The Bangalore Metro Rail Corporation Limited (BMRCL) has confirmed that civil works, including all 16 elevated stations across the Yellow Line, have been completed. Interior station finishing, platform installations, passenger amenities, and Communication-Based Train Control (CBTC) signaling systems are now fully in place.
The Yellow Line will offer much-needed connectivity to key zones like Electronic City, Bommanahalli, HSR Layout, and Silk Board, linking them with the Green Line at RV Road interchange and eventually the upcoming Blue and Pink Lines.
Safety inspections to begin mid-July
The final safety green signal is awaited from the Commissioner of Metro Rail Safety (CMRS). The Independent Safety Assessment (ISA), a crucial prerequisite, is set to begin post-July 15. Officials believe the inspections and approvals should be completed swiftly, barring any technical red flags.
Expected launch timeline: Late July to early August
With most infrastructure in place and test runs underway, BMRCL officials are targeting a phased launch between late July and early August 2025. If safety inspections proceed smoothly, the line may open initially with partial services, followed by full operations as more trainsets are inducted.
This timeline marks a significant step forward for Bengaluru’s metro network, which has faced repeated delays due to procurement issues, COVID-19 disruptions, and regulatory hurdles.
What the Yellow Line means for commuters
- Length: 18.8 km elevated corridor
- Stations: 16, including Electronic City, Hosa Road, Kudlu Gate, and RV Road
- Interchanges: Green Line (RV Road), future Blue Line (Central Silk Board), and Pink Line
- Train Type: Driverless with CBTC signaling
- Benefits: Reduced commute time from Electronic City to city centre, enhanced last-mile connectivity
You may also like
'If Marathi or Maharashtra is insulted ... ': Aaditya Thackeray issues 'things can escalate' warning; language row heats up
Diogo Jota was days away from Liverpool return as reason for fatal car trip revealed
Keir Starmer's plan to 'rewire' NHS explained – why you won't have to go to hospital
Torrid co-star affair rocked All Creatures Great and Small behind the scenes
Modi govt's record on environment protection not reliable: Jairam Ramesh